NewsFlash#03 April 07
NewsFlash#02 November 06
NewsFlash#01 August 06
Newsletter#06 Sept 05
Newsletter#05 March 05
Newsletter#04 December 04
Newsletter#03 July 04
Newsletter#02 April 204
Newsletter#01 March 04

 

NEWS ARCHIVE

newsflash_small_logo.png14 August 2006
4GLS Newsletter NewsFlash »
issue#01 August 2006

 


6th July 2006
4GLS User Meeting 2006 »

next_steps1.png

8 September 2006, Daresbury Laboratory.
An information and interaction meeting for potential users following publication of the Conceptual Design Report.
PDF Flyer »


13th April 2006
Conceptual Design Report4GLS Conceptual Design Report »
This report covers design work and ethos for 4GLS to date. Further design activities will continue over the coming year and your comments and thoughts on any aspect of the report are very welcome.


esffals.png


January 2006
2 New Job Opportunities
Laser System Manager
Postdoctoral Research Associate

September 2005
ERLP Sub-System Assembly and Test Activities
Assembly and testing is currently underway of sub systems for the ERLP in the DL Assembly Hall at the rear of the Stores building. The facility consists of an ISO 5 clean room, insertion device construction room, magnet test room and large capacity assembly hall for the range of collaborative projects involving technical build and measurement work at DL. Almost all of the capacity at present is taken up by ERLP to ensure that the project milestones are met.
more from newsletter#06»


March 2005
£1.6 Million in Funding
Additional funding, of £1.6M over the next two years, for technical design work on 4GLS has just been announced.
Further details and opportunities will be posted soon on the 4GLS web.
more from newsletter#05»


December 2004
Start-to-end-Simulations
The first start-to-end simulations for transportation of the electron beam around ERLP have been completed. To verify the predicted performance of the ERLP and its free electron laser (FEL), an integrated study of the overall beam dynamics of the accelerator has been carried out.
more from newsletter#04»


July 2004
EuroFEL Bid TOPS the List
The 4GLS team have been successful in attracting EU FP6 Design Studies funding as key participants in ‘EUROFEL’. In total Euro9M has been approved for work to run for three years starting in April 2005.
more from newsletter#03 »


April 2004
4GLS Moves into SRD
In a very positive move, the SR Director Mike Chesters has taken 4GLS and the ERL Prototype project into the SRD fold. This will ensure full representation of both projects at senior levels.
more from newsletter#02 »


March 2004
The CCLRC Programme Board approved
an increased total resource allocation of £13.922M for the project. A further £0.8M is to be held in reserve as contingency. The project will run over four years, the deadline for the construction of the ERL Prototype remains at March 2006.
more from newsletter#01 »


2nd April 2003
Ministers give go-ahead for the next development stage of 4GLS in Cheshire.
The building of the world-leading 4GLS (4th generation light source) has come one step closer with the announcement today of £11.5 million for an exploratory phase of the project. This phase involves a 3-year study to establish the technical know-how needed to build this innovative scientific research facility, including the construction of a prototype test facility.
... more »


13th December 2002
Science Minister Lord Sainsbury comes to Daresbury to discuss 4GLS

Science Minister Lord Sainsbury comes to Daresbury to discuss 4GLS


1st November 2002
4GLS gets green light from Office of Government Commerce Gateway 1 review.